Project Management: Core Concepts & Formulas
A typical university PM course blends governance (charters/baselines), planning (scope, schedule, cost), execution and control (change, risk, quality), and delivery approaches (predictive, agile, hybrid). This page focuses on the concepts you apply repeatedly and the equations you compute on exams and in practice.
1) Foundations & Baselines
Core idea: project control is baseline management. You define what “success” means, you set baselines, you measure deviation, and you decide when/what to change (governance).
Constraints and the performance model
| Constraint | Operational meaning |
|---|---|
| Scope | What is included/excluded; acceptance criteria; WBS boundaries. |
| Schedule | When outputs are delivered; dependencies; critical path and float. |
| Cost | Budget and funding; burn; forecasts; procurement commitments. |
| Quality | Fitness for use; defect rates; verification/validation plan. |
| Risk | Uncertainty that matters; threats/opportunities; reserves. |
Baseline types (exam-friendly)
Scope baseline (scope statement + WBS + WBS dictionary), schedule baseline (approved model + dates), and cost baseline (time-phased budget). Change control governs modifications to these baselines.
2) Scope, WBS, & Estimating
The Work Breakdown Structure (WBS) is the backbone of predictive planning: it decomposes deliverables into manageable work packages that can be estimated, assigned, scheduled, and controlled.
Estimation accuracy concepts
- Analogous (top-down): fast, less precise.
- Parametric: uses rates (e.g., cost per unit) and drivers.
- Bottom-up: slower, often more accurate when decomposition is strong.
Common “back-of-the-napkin” formulas
Cost = Effort × Labor rate + Materials + Other direct costs
3) Scheduling: CPM (Critical Path) & Float
Core CPM logic
CPM computes earliest and latest times across a dependency network. The critical path is the longest-duration path (zero total float) that determines the minimum project duration.
Forward pass (earliest times)
EF(activity) = ES(activity) + Duration(activity)
Backward pass (latest times)
LS(activity) = LF(activity) − Duration(activity)
Float (slack)
Why CPM matters beyond exams
CPM is the foundation for schedule risk analysis, change impact analysis, critical chain discussions, and credible execution forecasts. Even agile programs often maintain a dependency network at the feature/release level.
4) Uncertainty: PERT & Probabilistic Thinking
PERT addresses uncertain durations by using three-point estimates and computing an expected value and variance. (This is a simplification, but it’s a standard intro tool.)
PERT expected duration
O = optimistic, M = most likely, P = pessimistic
PERT activity variance (classic)
Standard deviation (σ) = (P − O) / 6
5) Cost Control: Earned Value Management (EVM)
EVM integrates scope, schedule, and cost by comparing what you planned to do (PV), what you actually accomplished (EV), and what you spent (AC).
Core EVM variables
EV (Earned Value) = budgeted cost of work performed
AC (Actual Cost) = actual cost of work performed
Variances
SV (Schedule Variance) = EV − PV
Performance indices
SPI (Schedule Performance Index) = EV / PV
Forecasting
EAC (simple) = BAC / CPI
ETC = EAC − AC
VAC = BAC − EAC
To-Complete Performance Index (TCPI)
TCPI (to meet EAC) = (BAC − EV) / (EAC − AC)
Interpretation shortcuts
CPI < 1 → over budget for earned progress. SPI < 1 → behind schedule (in EV terms). Variances can be negative/positive; indices give normalized “how bad/how good.”
6) Risk: EMV, Expected Loss, Prioritization
Risk management formalizes uncertainty: identify, analyze (qual + quant), plan responses, monitor. Intro courses typically emphasize probability–impact thinking and decision analysis basics.
Expected Monetary Value (EMV)
Risk exposure (simple)
Decision tree expected value
Often used for make/buy decisions, response options, and evaluating whether mitigation cost is justified by expected loss reduction.
7) Communications & Stakeholders
Projects fail socially before they fail mathematically. Stakeholder alignment, decision rights, and information cadence are control mechanisms.
Communication channels (classic exam formula)
Where n is the number of stakeholders/participants in a communication network. This models why coordination cost rises nonlinearly with team size.
8) Resources & Capacity
Resource planning translates scope into staffing, equipment, and constraints. The math is often simple; the challenge is constraints and contention.
Utilization and capacity (simple)
Capacity (per period) = Available hours × Productivity rate
Why “100% utilization” breaks projects
High utilization reduces flexibility, increases queueing delays, and amplifies variability. Many modern PMO operating models intentionally hold capacity buffers.
9) Agile/Lean Metrics & Flow
Modern courses increasingly include agile and hybrid delivery. While agile de-emphasizes upfront deterministic baselines, it still uses rigorous measurement—especially flow metrics.
Velocity (team-specific)
Flow metrics
Cycle Time = Time from start to finish for an item
Lead Time = Time from request to delivery
Little’s Law (useful in Kanban/flow contexts)
10) References & Free Material
Authoritative sources you can cite and link in course work or professional documentation:
PMI (global PM standard and guidance)
- PMI — PMBOK® Guide / The Standard for Project Management (overview)
- PMI — Project Performance Domains (PDF)
ISO standard guidance
GAO best-practice guides (schedule and cost reliability)
- GAO — Schedule Assessment Guide (GAO-16-89G) (PDF)
- GAO — Cost Estimating and Assessment Guide (GAO-20-195G) (PDF: download)